Gabion Wall Construction at White City, West London
Project Overview
AGA Group Enviro-Fix Ltd (AGA) was subcontracted by Erith, the principal contractor, to deliver a technically demanding gabion wall installation at the Imperial College site in White City, West London. The project formed part of a wider redevelopment initiative, requiring precision engineering and close coordination with existing structural elements.
Scope of Works
AGA was responsible for the construction of a 35-metre long gabion wall, with the following specifications:
- Height: 3 metres
- Depth: 2 metres
- Integration: The wall had to tie into pre-installed sheet piling, which significantly constrained the available space for backfilling.
Due to the limited tolerance for deviation and the need to integrate seamlessly with existing infrastructure, accuracy was paramount to achieving the desired structural and aesthetic finish.
Project Overview
AGA Group Enviro-Fix Ltd (AGA) was subcontracted by Erith, the principal contractor, to deliver a technically demanding gabion wall installation at the Imperial College site in White City, West London. The project formed part of a wider redevelopment initiative, requiring precision engineering and close coordination with existing structural elements.
Scope of works
AGA was responsible for the construction of a 35-metre long gabion wall, with the following specifications:
- Height: 3 metres
- Depth: 2 metres
- Integration: The wall had to tie into pre-installed sheet piling, which significantly constrained the available space for backfilling.
Due to the limited tolerance for deviation and the need to integrate seamlessly with existing infrastructure, accuracy was paramount to achieving the desired structural and aesthetic finish.
- Erith Contractors
- White City, West London
- £8,955
- Completed December 2020 (6 days)
Technical Challenges & Solutions
The gabion wall had to be constructed in a confined area with minimal space for backfilling, as it was required to tie directly into the sheet piling already in place. This posed a challenge in terms of both logistics and structural integrity.
AGA’s team employed precise surveying techniques and careful staging of materials to ensure that the wall aligned perfectly with the sheet piling. The use of laser levels and tight quality control checks throughout the build ensured that tolerances were maintained and the final structure met all design specifications.
Coordination with Main Contractor
As a subcontractor to Erith, AGA maintained close communication and coordination throughout the project. This included:
- Regular site meetings to align on progress and sequencing
- Joint reviews of technical drawings and tolerances
- Collaborative problem-solving to address site-specific constraints
Project Management Approach
AGA applied its task-led monitoring system to ensure the project remained on schedule and met quality expectations. Key elements included:
- Daily progress tracking against the programme
- Performance analysis to identify and resolve inefficiencies
- Trigger point management for material deliveries and resource allocation
- Proactive scheduling adjustments to mitigate potential delays
Outcome
The gabion wall was completed to specification, on time, and with minimal disruption to surrounding works. The successful integration with existing sheet piling demonstrated AGA’s capability in precision construction, collaborative delivery, and problem-solving under constraint.
This project highlights AGA’s strengths in:
- Working within tight tolerances
- Delivering high-quality outcomes in complex environments
- Supporting main contractors with reliable and responsive subcontracting services
Photos below show work in progress
Enviro-Fix (A.G.A. Group)
Environmental Contractors
Engineering Nature
If you have a question or enquiry, please do not hesitate to call our team. If it is outside business hours, drop us an email – we’d love to hear from you