Restoration of Cotton Pond, Sanders Park
Project Overview
Sanders Park, covering 16.3 hectares to the west of Bromsgrove, Worcestershire, is one of the town’s most valued public green spaces. The park forms a vital link between the urban centre and the countryside beyond and incorporates the small valley of the Battlefield Brook, a natural landscape feature that has played an important role in Bromsgrove’s heritage for centuries.
In 2024, Bromsgrove District Council commissioned Enviro-Fix to undertake essential restorative works to the park’s pond which was built in the 1960’s. The project aimed to remove accumulated silt, restore water flow, enhance ecological value, and safeguard surrounding pathways. All works were carried out within a three-week programme in November 2024.
Project Overview
Sanders Park, covering 16.3 hectares to the west of Bromsgrove, Worcestershire, is one of the town’s most valued public green spaces. The park forms a vital link between the urban centre and the countryside beyond and incorporates the small valley of the Battlefield Brook, a natural landscape feature that has played an important role in Bromsgrove’s heritage for centuries.
In 2024, Bromsgrove District Council commissioned EnviroFix to undertake essential restorative works to the park’s pond which was built in the 1960’s. The project aimed to remove accumulated silt, restore water flow, enhance ecological value, and safeguard surrounding pathways. All works were carried out within a three-week programme in November 2024.
- Bromsgrove District Council
- Worcestershire
- £32,761
- Completed November 2024 (3 weeks)
Project Objectives
- Restore the pond’s capacity and improve water quality
- Address blocked flows and structural issues within the outlet
- Improve habitat diversity, including installation of a new reed bed
- Protect surrounding infrastructure at risk from erosion
- Manage and repurpose excavated silt sustainably within the park
The pond before works commenced
Scope of Works
EnviroFix delivered a comprehensive package of environmental and civil works, including:
- Mobilisation of all plant, equipment, and materials
- Installation of a bung at the inlet to stop incoming flow
- Opening the outlet and fully dewatering the pond using a pump
- Ethical removal of fish (AGA Group are licenced by the Environment Agency to remove and transport live fish).
Pond and Island Restoration
- Installation of a new pipe section and concrete works within the outlet chamber
- Vegetation clearance around the perimeter of the island
- Construction of a 500 mm high gabion wall along one side of the island to form the base of a new reed bed
- Use of recovered silt to backfill and establish the new reed bed
Silt Removal and Site Regrading
- Remaining silt removed from the pond and placed in a designated bunding area close to the pond area.
- Localised repairs carried out to brickwork and concrete where pathways were at risk of collapse due to undermining or missing edging
The following photographs show work in progress.
Completion Works
- Demobilisation and final site tidying
Programme
Week 1
- Pond dewatering
- Fish removal
- Outlet repair and works to delete redundant elements
- Vegetation clearance
- Initial desilting and bund formation
Week 2
- Installation of the gabion-supported reed bed
- Continued desilting operations
Week 3
- Final desilting
- Minor structural wall repairs
- Planting and establishment works
Results and Outcomes
Flourishing wildflower planted on silt bund area
The project successfully restored the pond’s functionality, improved biodiversity, and strengthened structural elements around the waterbody. One of the standout outcomes was the creation of a new wildflower area, established on the silt bund constructed by EnviroFix. Following establishment, this area has become a vibrant feature of the landscape adjacent to the pond, enhancing ecological value and visitor experience.
Client Feedback
“We are really happy with the quality of the work and can’t wait to see the planting areas as they establish. I appreciate Jake’s time and patience in getting the work over the line after a challenging year with weather and a busy park schedule.”
Richard Hickman BSc (Hons)
Horticultural Specialist: Bromsgrove District and Redditch Borough Councils
Parks and Events Team
Enviro-Fix (A.G.A. Group)
Environmental Contractors
Engineering Nature
If you have a question or enquiry, please do not hesitate to call our team. If it is outside business hours, drop us an email – we’d love to hear from you