Pond De-silting and Enhancement Works

Project Overview

A.G.A. Group was appointed by Maidstone Borough Council to carry out pond de-silting and associated enhancement works across three public parks in Kent. Delivered in two phases, the project aimed to:

  • Improve water quality
  • Restore ecological balance
  • Enhance public access and amenity value

As part of the works, A.G.A. Group successfully de-silted lakes at all three sites. At Mallards Way, additional enhancements were completed, including the installation of platforms, hydroseeding, and planting to further enrich the landscape and biodiversity.

Mote Park and Whatman Park Ponds

  • Mote Park: Pond de-silting and silt bunding completed over two weeks starting 17th September 2024.
  • Whatman Park: Pond de-silting and silt bunding completed over two weeks starting 9th September 2024.

These works focused on sediment removal and bunding to improve water flow, reduce stagnation, and support aquatic habitat restoration.

Project Overview

A.G.A. Group was appointed by Maidstone Borough Council to carry out pond de-silting and associated enhancement works across three public parks in Kent. Delivered in two phases, the project aimed to:

  • Improve water quality
  • Restore ecological balance
  • Enhance public access and amenity value

As part of the works, A.G.A. Group successfully de-silted lakes at all three sites. At Mallards Way, additional enhancements were completed, including the installation of platforms, hydroseeding, and planting to further enrich the landscape and biodiversity.

Mote Park and Whatman Park Ponds

  • Mote Park: Pond de-silting and silt bunding completed over two weeks starting 17th September 2024.
  • Whatman Park: Pond de-silting and silt bunding completed over two weeks starting 9th September 2024.

These works focused on sediment removal and bunding to improve water flow, reduce stagnation, and support aquatic habitat restoration.

Mallards Way Pond

Works commenced on 3rd October 2024 and continued for six weeks, with a second phase completed in April 2025 over three weeks.

Key activities included:

  • De-silting operations using an amphibious excavator.
  • Installation of bank protection systems including Nicospan, gabions, and board edging.
  • Installation of 8 metres of pre-vegetated coir rolls on a brushwood faggot, with backfill to cover exposed pipework.
  • Construction of 4 fishing platforms made from recycled plastic:
    • Bank A: Two platforms, each 3m wide and 1.5m deep, with fill material and path levelling.
    • Bank B: Two platforms, each 1.8m wide and 2m deep.
  • Installation of a replacement outlet structure:
    • Althon Headwall H6C A with 1100mm back wall height and 375mm ID pipe opening.
    • GMS close-coupled grating and channel-mounted stoplog system with 5x 100mm aluminium stoplogs, locking brackets, and lifting hooks.
  • Groundworks including MOT installation to the backs of fishing platforms and along the northern bank path edge to achieve level access.
  • Hydroseeding using wildflower and wetland seed mix to the area behind the bank revetment.

Project Outcome

The project was delivered successfully across all three sites, improving the ecological health and usability of the ponds. The installation of fishing platforms and bank protection features enhanced public access and safety, while the use of sustainable materials and sensitive construction methods ensured minimal environmental impact.

Photographs of completed works shown below