Pond Lining using Geosynthetic Clay Liner
Project Overview
AGA Group was contracted by Morton Pattison to install a Geosynthetic Clay Liner (GCL) for a newly excavated pond at a rural site near Andover. The objective was to create a watertight barrier to support the pond’s long-term environmental and functional performance.
Pond Preparation
The subgrade was carefully inspected prior to liner installation to ensure it was smooth, free from sharp objects, and suitable for receiving the GCL.
This step was essential to prevent damage to the liner and to ensure a stable base for the subsequent layers.
Project Overview
AGA Group was contracted by Morton Pattison to install a Geosynthetic Clay Liner (GCL) for a newly excavated pond at a rural site near Andover. The objective was to create a watertight barrier to support the pond’s long-term environmental and functional performance.
Pond Preparation
The subgrade was carefully inspected prior to liner installation to ensure it was smooth, free from sharp objects, and suitable for receiving the GCL.
This step was essential to prevent damage to the liner and to ensure a stable base for the subsequent layers.
- Morton Pattison
- Tangley, Andover
- £31,446
- Completed September 2025 (2 weeks)
Liner Deployment
GCL rolls were laid in 5-metre-wide sections, with longitudinal edges aligned along the slope direction where applicable. A minimum overlap of 300mm was maintained between adjacent rolls, with additional allowance made to accommodate any potential movement.
Each roll was positioned to and from anchor trenches to ensure secure edge containment and long-term stability.
Joint Sealing
To ensure watertight joints, 25kg bags of bentonite powder were applied at cross-seam overlaps (roll ends). In areas requiring enhanced sealing, a bentonite paste—prepared by mixing one part bentonite with four to six parts water—was applied over a minimum 200mm area, while still maintaining the 300mm overlap. Bentonite powder was also applied around all penetrations, such as pipework, to maintain the integrity of the liner system.
Liner Handling and Cutting
Operatives ensured that the liner was free of tension before cutting, which helped reduce the risk of swinging or uncontrolled movement. All cuts were made using sharp retractable Stanley knives in a single, straight motion to avoid accidental damage or injury.
Throughout the process, appropriate PPE was worn, and tag lines were used to control suspended loads, ensuring safe handling and accurate positioning.
Cover Placement
Once the liner was in place, a minimum of 300mm of well-compacted soil was placed over it to protect the liner and match the final pond profile. The soil was sourced from on-site stockpiles and transported using wheeled dumpers to minimise ground disturbance and maintain efficiency.
Overnight Protection
To protect the liner during non-working hours, all exposed areas were covered overnight with the required 300mm of soil, except for joining overlaps up to 750mm. If any liner was left uncovered and became saturated, additional bentonite powder was applied to restore the required sealing performance.
Weather Considerations
Installation was not carried out during extreme weather conditions or in standing water. This precaution was taken to prevent premature hydration of the liner and to ensure proper compaction of the cover material.
Health & Safety Measures
All lifting operations involving the liner were conducted using tag lines to control swing and reduce risk. Operatives maintained a safe distance from suspended loads and followed test lift procedures before final placement. All activities were carried out in compliance with site-specific risk assessments and method statements (RAMS). Additional care was taken on this site due to the presence of overhead power lines, which were closely monitored.
Daily briefings were held to ensure all site staff were aware of the associated risks and safety protocols.
Project Outcome
The GCL installation was completed on time and in full accordance with the project specification. All quality checks were passed, and the client signed off on the completed works. The pond now features a robust, impermeable base, supporting the project’s environmental goals and ensuring long-term functionality.
The following photographs show work in progress and on completion: