Reed Bed Installation at Lee Valley Ice Centre
Project Overview
A.G.A. Group was commissioned by Buckingham Group to install a reed bed system at the Lee Valley Ice Centre. The reed bed was designed to enhance natural wastewater treatment through ecological engineering.
The project involved the full excavation, lining, and planting of a reed bed, following detailed technical specifications.
Client Objectives
- Implement a low-maintenance, sustainable wastewater treatment solution.
- Ensure compliance with environmental regulations.
- Enhance biodiversity and landscape integration.
Project Overview
A.G.A. Group was commissioned by Buckingham Group to install a reed bed system at the Lee Valley Ice Centre. The reed bed was designed to enhance natural wastewater treatment through ecological engineering.
The project involved the full excavation, lining, and planting of a reed bed, following detailed technical specifications.
Client objectives
- Implement a low-maintenance, sustainable wastewater treatment solution.
- Ensure compliance with environmental regulations.
- Enhance biodiversity and landscape integration.
- Buckingham Group
- Lee Valley Ice Centre
- £32,000
- Completed August 2022 (2 weeks)
Site Preparation
- A CAT scan was conducted prior to excavation to identify and avoid underground utilities.
- All vegetation and topsoil were carefully removed to prepare the site for excavation.
Excavation
- The reed bed was excavated according to the engineering drawings provided by the main contractor.
- Arisings from the excavation were transported to a designated soil bund area, where they were profiled by the digger as needed.
- The excavator compacted the base and sides of the reed bed to ensure structural integrity.
- Sharp stones were removed to protect the liner.
- Trenches were dug to accommodate inlet and outlet pipes.
Lining Installation
- A needle-punched underlay was laid on the base of the reed bed.
- A liner was then installed, folded back temporarily while anchor trenches were dug.
- The liner was folded into the trenches and backfilled to secure it.
- ‘Witches hats’ were placed around the inlet and outlet pipes, sealed with tape, glue, and jubilee clips to ensure watertight connections.
- A second layer of needle-punched underlay was laid over the liner for added protection.
Gravel and Planting
- Gravel was installed to the specified depths and raked level.
- Once water was present, reed plants from our were hand-planted into the gravel to initiate the natural filtration process, along with additional marginal and aquatic plants which were all grown at our large nursery in Norfolk.
Plants growing on at our Norfolk nursery:
Challenges and Solutions
- Precision excavation was required to match design specifications and avoid damage to surrounding areas.
- Pipe sealing demanded careful attention to detail to ensure long-term durability and leak prevention.
Outcomes & Benefits
- A fully functional reed bed system now provides natural filtration of wastewater.
- The installation supports biodiversity, improves landscape aesthetics, and reduces reliance on mechanical treatment systems.
- The project demonstrates A.G.A. Group’s commitment to sustainable engineering and environmental stewardship.