Installation of Geosynthetic Clay Liner to Attenuation Pond

Project Overview

As part of the sustainable drainage strategy for a new housing development in Worksop, an attenuation pond was constructed to manage surface water runoff. To ensure long-term impermeability and environmental compliance, a Geosynthetic Clay Liner (GCL) was specified for the pond lining.

This case study outlines the methodology, installation process, and demobilisation procedures undertaken during the project.

Project Overview

As part of the sustainable drainage strategy for a new housing development in Worksop, an attenuation pond was constructed to manage surface water runoff. To ensure long-term impermeability and environmental compliance, a Geosynthetic Clay Liner (GCL) was specified for the pond lining.

This case study outlines the methodology, installation process, and demobilisation procedures undertaken during the project.

Liner Deployment

  • The GCL was delivered to site in rolls, each measuring 5 metres in width.
  • Installation commenced by rolling out the liner in 5m wide sections, ensuring a consistent overlap between adjacent sheets as per manufacturer guidelines.
  • Care was taken to avoid damage to the liner during handling and placement. All personnel involved were trained in GCL handling procedures.

Soil Cover Placement

  • Once the liner was in place, a minimum of 300mm of soil cover was applied across the entire surface to protect the liner from UV degradation, mechanical damage, and desiccation.
  • Soil was sourced from an on-site stockpile and transported to the pond area using a wheeled dumper to minimise ground disturbance.
  • The soil was then spread evenly over the liner using an excavator and compacted in layers to achieve the required density and stability.

Detailing Around Structures

  • Special attention was given to the headwall structure within the pond.
  • The liner was carefully cut and shaped to fit around the headwall, ensuring a watertight seal.
  • To secure the liner, it was mechanically fixed by drilling into the base of the headwall and attaching a steel termination bar, which was bolted in place to prevent movement or uplift.

Site Clean-Up

  • Upon completion of the liner installation and soil cover works, all materials, equipment, and waste were removed from the site in accordance with environmental and safety regulations.

Ground Remediation

  • Any areas of ground disturbed or damaged during the works were reinstated to an acceptable standard, including regrading and reseeding where necessary.

Client Sign-Off

  • A final inspection was conducted with the client to verify that all works had been completed to specification.
  • Upon satisfaction, the client provided formal sign-off of the completed works.

Site Security

  • The site was left in a safe and secure condition, with all access points closed and any temporary fencing or signage removed or made safe.

Photographs below show work in progress: