Kett’s Heights Access and Landscaping works

Project Overview

Completed in March 2024, the project involved the construction of a new 22.5-metre ramped access path linking Ladbrook Place car park to the open space, alongside the resurfacing and refurbishment of a 65-metre stepped path from the Kett’s Hill entrance.

These improvements were designed to enhance connectivity while preserving the site’s heritage and natural character.

Accessibility and Stabilisation Improvements at Kett’s Heights, Norwich

Kett’s Heights is a historically significant open space owned by Norwich City Council. Characterised by steep woodland terrain, the site features the remains of a medieval chapel, 19th-century garden terraces, and one of Norwich’s three strategic viewpoints.

AGA Group Enviro-Fix Limited (AGA) was appointed as Principal Contractor to deliver a programme of works aimed at improving accessibility across the site, ensuring it could be safely and inclusively enjoyed by all visitors.

Project Overview

Completed in March 2024, the project involved the construction of a new 22.5-metre ramped access path linking Ladbrook Place car park to the open space, alongside the resurfacing and refurbishment of a 65-metre stepped path from the Kett’s Hill entrance.

These improvements were designed to enhance connectivity while preserving the site’s heritage and natural character.

Accessibility and Stabilisation Improvements at Kett’s Heights, Norwich

Kett’s Heights is a historically significant open space owned by Norwich City Council. Characterised by steep woodland terrain, the site features the remains of a medieval chapel, 19th-century garden terraces, and one of Norwich’s three strategic viewpoints.

AGA Group Enviro-Fix Limited (AGA) was appointed as Principal Contractor to deliver a programme of works aimed at improving accessibility across the site, ensuring it could be safely and inclusively enjoyed by all visitors.

Site Challenges and Engineering Solutions

Due to the site’s steep gradients and variable ground conditions, significant excavation was required both along the existing paths and within the area designated for the new ramp. To facilitate access for construction, a section of boundary wall was carefully dismantled and later replaced with new gate piers and gates, seamlessly integrating the ramp with the car park.

To stabilise the terrain and support the new infrastructure, two gabion retaining walls were constructed:

  • Upper Gabion Wall: Installed to reinforce the bank above the ramp, preventing soil movement and erosion.
  • Lower Gabion Wall: Engineered to support the ramp structure and its foundations. This wall was fitted with bollards and a handrail to mitigate fall risks and serve as a crash barrier for vehicles accessing the site.

These interventions not only stabilised the embankment but also ensured long-term durability and safety for users.

Collaboration and Compliance

Throughout the project, AGA’s project manager worked in close coordination with the Council’s representative and Cadent to ensure all works were carried out in compliance with relevant protocols, particularly in relation to the high-pressure gas main running through the site. This proactive engagement ensured that all utility-related risks were effectively managed and mitigated.

Project Outcome

The completed works have transformed Kett’s Heights into a more accessible and secure public space, while respecting its historical and environmental significance. The new ramp and refurbished paths provide safe and inclusive access for a wider range of visitors, and the stabilisation measures ensure the long-term resilience of the site’s infrastructure.

The following photographs show sections of the work in progress and following completion. 

All works were completed on time and to the Client’s complete satisfaction and the following feedback was received on completion of the project:

Contractor’s Feedback on Kett`s Heights Access Improvements

A.G.A Group Enviro Fix Ltd. was awarded to complete the accessibility improvement works on the former gasworks site, Kett’s Heights in October 2023. The works included the resurfacing of the existing pedestrian infrastructure and the construction of a new vehicular entrance with a compliant ramp from Ladbrooke Place Car Park to the open green space and viewing points to the city of Norwich. 

Jake and the team had to work and follow instructions in multidisciplinary environment, liaise with utility companies including Cadent Gas and Anglian Water, as well as communicate to local stakeholder groups and the public on a daily basis.    

During the excavation works the team encountered with several unchartered services, such as abandoned pipe works and an underground chamber. These complications were always handled in a safe and professional manner that included reporting the findings, securing the site and hold off the works until further instructions were received from the relevant statutory undertakers. The site levels and the proximity of the gas mains were a limiting factor in the use of heavy machinery; however, the team accommodated the challenging conditions, and a safe working method was designed around the pipes under the supervision of Cadent Gas. 

The staff developed a good relationship with the residing friends group and made sure that they are well informed of the site progress and could safely carry on with their weekly maintenance activities near the construction site. In collaboration with the open spaces manager and the Friends of Kett`s Heights, A.G.A Group installed a waterpipe for the group and were also commissioned to carry out the reseeding of the banked areas. 

Jake, Lloyd and the team were a pleasure to work with. Despite the complexity and uncertain factors of this project we found it very easy and efficient to coordinate with Jake to find the best solutions to the arisen issues and achieve a high-quality outcome. The excellent work done by the team has added value to Kett`s Heights and to the process of making public spaces more inclusive. 

We would certainly recommend A.G.A Group for a project of a similar nature.

Gabriella Mogyorosi 

Landscape Architect CMLI 

Planning 

Norwich City Council 

Enviro-Fix (A.G.A. Group)

Environmental Contractors

Engineering Nature

If you have a question or enquiry, please do not hesitate to call our team. If it is outside business hours, drop us an email – we’d love to hear from you