Beach Boardwalk Replacement Hayling Island
Project Overview
In May 2024, A.G.A. Group Enviro-Fix Limited (AGA) was appointed by Havant Borough Council to carry out the replacement of approximately 50 metres of accessible beach boardwalk, including a seating platform designed to enhance public enjoyment of the coastal environment.
The project was part of the council’s ongoing commitment to improving accessibility and safety along the seafront, while maintaining public access and minimising disruption to beach users and local residents.
Challenges and Considerations
One of the key challenges of the project was the need to keep the beach open to the public throughout the duration of the works. This included maintaining access for beach hut users, many of whom are regular visitors and residents.
To address this, AGA implemented a series of proactive site management strategies:
- Daily inspections and secure fencing were used to clearly demarcate work zones and ensure public safety.
- Material deliveries and on-site storage were carefully coordinated with the client’s representative to avoid peak usage times and minimise disruption.
- Clear signage and communication helped keep the public informed and reassured throughout the works.
Project Overview
In May 2024, A.G.A. Group Enviro-Fix Limited (AGA) was appointed by Havant Borough Council to carry out the replacement of approximately 50 metres of accessible beach boardwalk, including a seating platform designed to enhance public enjoyment of the coastal environment.
The project was part of the council’s ongoing commitment to improving accessibility and safety along the seafront, while maintaining public access and minimising disruption to beach users and local residents.
Challenges and Considerations
One of the key challenges of the project was the need to keep the beach open to the public throughout the duration of the works. This included maintaining access for beach hut users, many of whom are regular visitors and residents.
To address this, AGA implemented a series of proactive site management strategies:
- Daily inspections and secure fencing were used to clearly demarcate work zones and ensure public safety.
- Material deliveries and on-site storage were carefully coordinated with the client’s representative to avoid peak usage times and minimise disruption.
- Clear signage and communication helped keep the public informed and reassured throughout the works.
- Havant Borough Council
- Hailing Island
- £76,000
- Completed June 2024 (6 weeks)
Project Management Approach
AGA employed a task-led project monitoring system to ensure the works progressed efficiently and on schedule. This system included:
- A main programme timeline that identified both individual and interdependent tasks.
- Real-time tracking of progress, allowing the team to anticipate potential delays and reallocate resources proactively.
- A focus on schedule adherence, which is a core principle of AGA’s project management philosophy.
This structured approach enabled the team to maintain momentum and deliver the project within the agreed timeframe.
Client Collaboration
Throughout the project, AGA’s Project Manager maintained regular communication with the client’s representative. Scheduled on-site meetings were held at key milestones to review progress, address any concerns, and ensure alignment with the client’s expectations.
This collaborative approach fostered transparency and trust, and ensured that any adjustments could be made swiftly and effectively.
Project Outcome
The project was completed on time and to the full satisfaction of Havant Borough Council. The new boardwalk and seating platform now provide a safer, more durable, and accessible route for all beach users, enhancing the overall visitor experience.
AGA’s commitment to public safety, efficient project delivery, and client engagement was instrumental in the success of this coastal infrastructure improvement.
Photographs of completed works shown below