Epsom & Ewell Great Pond Remedial and Access Works

Project Overview

The Great Pond is located on Epsom Common in Surrey, a site designated as a Site of Special Scientific Interest (SSSI) in the 1950s and later as a Local Nature Reserve in 2001. These designations highlight the ecological importance of the area and the need for sensitive and sustainable management practices.

AGA Group was contracted by Epsom and Ewell Borough Council to carry out a series of improvement and conservation works aimed at enhancing access, safety, and environmental resilience around the pond and its associated infrastructure.

Scope of Works

The contracted works included:

    • Construction of 250 metres of access track
    • Widening of the crest path along the spillway
    • Lining of the downstream slope adjacent to the spillway
    • Refurbishment of stone fill on the steps of the downstream face of the dam
    • Gabion basket repairs
    • Installation of rip-rap to prevent erosion in the main spillway

Project Overview

The Great Pond is located on Epsom Common in Surrey, a site designated as a Site of Special Scientific Interest (SSSI) in the 1950s and later as a Local Nature Reserve in 2001. These designations highlight the ecological importance of the area and the need for sensitive and sustainable management practices.

AGA Group was contracted by Epsom and Ewell Borough Council to carry out a series of improvement and conservation works aimed at enhancing access, safety, and environmental resilience around the pond and its associated infrastructure.

Scope of Works

The contracted works included:

      • Construction of 250 metres of access track
      • Widening of the crest path along the spillway
      • Lining of the downstream slope adjacent to the spillway
      • Refurbishment of stone fill on the steps of the downstream face of the dam
      • Gabion basket repairs
      • Installation of rip-rap to prevent erosion in the main spillway

Gas Main Location

Prior to commencement, AGA liaised with the local gas network company to verify the location of a gas main, which was found to differ from the previously provided site plan. This proactive engagement ensured safe working conditions and avoided potential hazards.

Material Availability

One of the specified sub-base materials was unavailable. AGA’s project manager consulted with the client and proposed a suitable alternative, which was agreed upon, ensuring continuity of the project without compromising quality.

Project Management & Monitoring

AGA implemented a task-led monitoring system to track daily progress against the project timeline. This included:

  • Daily progress reviews of individual tasks
  • Analysis of shortfalls to identify inefficiencies or pinch points
  • Logging of objectives and outcomes against the programme
  • Trigger point tracking for material deliveries and resource allocation

This proactive approach enabled early identification of potential delays and allowed for dynamic reallocation of resources, helping to maintain adherence to the agreed schedule.

Project Conclusion

AGA’s commitment to collaborative problem-solving, environmental sensitivity, and rigorous project management ensured the successful delivery of works at The Great Pond. The project not only improved infrastructure and access but also supported the long-term conservation goals of Epsom Common.

The following photos show sections of the works following completion: