Installation of Coir Roll Revetment and Scour Protection
Project Overview
An established holiday park in the Lincolnshire Wolds undertook improvement works on two of its fishing lakes, which are nestled within a picturesque landscape and surrounded by luxury wooden lodges. The project aimed to enhance the ecological value and structural integrity of the lake edges while preserving the natural aesthetics of the park for its guests.
This involved the installation of pre-vegetated coir roll revetments and scour protection measures, designed to stabilise the banks, encourage vegetation growth, and safeguard vulnerable infrastructure.
Revetment Installation
A total of 166 metres of pre-vegetated coir roll revetment was installed, split between two lakes. The coir rolls were placed on a brushwood faggot base and backfilled with topsoil. Backfilling was carried out only in areas without existing vegetation, ensuring that no existing plant life was disturbed.
The coir rolls were positioned in front of existing vegetation to create a level, vegetated edge along the banks, enhancing both stability and biodiversity.
Project Overview
An established holiday park in the Lincolnshire Wolds undertook improvement works on two of its fishing lakes, which are nestled within a picturesque landscape and surrounded by luxury wooden lodges. The project aimed to enhance the ecological value and structural integrity of the lake edges while preserving the natural aesthetics of the park for its guests.
This involved the installation of pre-vegetated coir roll revetments and scour protection measures, designed to stabilise the banks, encourage vegetation growth, and safeguard vulnerable infrastructure.
Revetment Installation
A total of 166 metres of pre-vegetated coir roll revetment was installed, split between two lakes. The coir rolls were placed on a brushwood faggot base and backfilled with topsoil. Backfilling was carried out only in areas without existing vegetation, ensuring that no existing plant life was disturbed.
The coir rolls were positioned in front of existing vegetation to create a level, vegetated edge along the banks, enhancing both stability and biodiversity.
- Award Winning Holiday Park
- Lincolnshire
- £30,910
- Completed February 2024 (3 weeks)
Scour Protection Measures
To protect the bank area beneath a cabin, scour protection was installed using MacMat R—a mesh-reinforced, three-dimensional geomat designed for erosion control on sloped embankments. The mat was secured with J-pins and covered with small RipRap stone to form a durable and effective bank protection system.
Demobilisation
Upon completion of the works, all plant and equipment were demobilised, and the site was left in a stable and enhanced condition, with improved erosion resistance and ecological value
Photographs show areas of work in progress and following completion